2009 Concrete Sidewalk Contract No. 1

  • Advertisement for Bids
  • Plan Holders List (updated daily)
  • Addendum (if applicable)
  • Bid Tabulation (TBA August 19th)
  • Progress Reports
    • October 16, 2009 – The concrete work was completed this week.
    • October 9, 2009 – The sidewalk has been delayed due to weather. It is approximately 75% complete and will be finished in 4-5 days once weather permits.
    • October 2, 2009 – Construction of the concrete walkway continues.
    • September 25, 2009 – Concrete work has been progressing on the new sidewalk along TH-13 with about 60% completed.
    • September 18, 2009 – The contractor has been grading for new sidewalk and have started placing new concrete.
    • September 11, 2009 – The contractor has started grading operations.