2009 Concrete Sidewalk Contract No. 1
- Advertisement for Bids
- Plan Holders List (updated daily)
- Addendum (if applicable)
- Bid Tabulation (TBA August 19th)
- Progress Reports
- October 16, 2009 – The concrete work was completed this week.
- October 9, 2009 – The sidewalk has been delayed due to weather. It is approximately 75% complete and will be finished in 4-5 days once weather permits.
- October 2, 2009 – Construction of the concrete walkway continues.
- September 25, 2009 – Concrete work has been progressing on the new sidewalk along TH-13 with about 60% completed.
- September 18, 2009 – The contractor has been grading for new sidewalk and have started placing new concrete.
- September 11, 2009 – The contractor has started grading operations.