2025 State Aid Overlay Project Updates – Job 2502

September 5, 2025 – Sod was placed this week, the only work remaining is paint striping and punch list items.

August 28, 2025 – The bituminous overlay was placed this week. Work remaining includes paint striping, turf restoration, punch list items, and general cleanup.

August 21, 2025 – The contractor performed the edge milling today and continued repairs to the manholes and catch basins in the project area. Placement of the overlay is scheduled for next week.

August 14, 2025 – The contractor began replacing curb and gutter this week. Work expected next week includes completion of concrete work, repairs to manholes and catch basins, and edge milling. The bituminous overlay for this project is scheduled for August 25-30.

August 1, 2025 – Ulland Brothers will start work on this project the week of August 4-8. The first phase of the project will be the replacement of settled or damaged sections of concrete curb & gutter, and repairs to manholes and storm sewer inlets in the project area. This work is expected to take two to three weeks. Once this work is complete, the contractor will begin the process of edge milling and overlaying the street.