2025 State Aid Overlay Project – Job 2502
August 14, 2025 – The contractor began replacing curb and gutter this week. Work expected next week includes completion of concrete work, repairs to manholes and catch basins, and edge milling. The bituminous overlay for this project is scheduled for August 25-30.
August 1, 2025 – Ulland Brothers will start work on this project the week of August 4-8. The first phase of the project will be the replacement of settled or damaged sections of concrete curb & gutter, and repairs to manholes and storm sewer inlets in the project area. This work is expected to take two to three weeks. Once this work is complete, the contractor will begin the process of edge milling and overlaying the street.