2026 State Aid Street Overlay Project Updates- Job 2602
October 2, 2026 – The sod installation was completed on all streets this week. The only work remaining is paint striping, minor cleanup and punch list items.
September 25, 2026 – Grading and sod placement continued this week, and completion is expected next week. Pavement markings, including centerline striping, parking stalls, and crosswalks, are scheduled to be installed tomorrow.
September 18, 2026 – This week the sod placement was completed. Next week they will complete the sod placement and also complete the pavement markings (centerline striping, crosswalks, parking stalls, etc.).
September 9, 2026 – The contractor continued grading and prepping the disturbed areas for sod in all areas of the project. The sodding subcontractor is scheduled to begin placing sod later this week.
August 21, 2026 – The contractor began placing the bituminous overlays and will finish on all streets by the end of today. The concrete subcontractor is scheduled to return next week to resume sidewalk replacements.
July 17, 2026 – The contractor continued making repairs to manholes and catch basins in the project areas and began sawcutting pavement along portions of curb & gutter identified for replacement. The concrete subcontractor has pushed their schedule back and now anticipates beginning replacement the week of July 27-31.
July 2, 2026 – The contractor anticipates beginning work on the manhole and catch basin repairs next week. The concrete subcontractor is still tentatively scheduled to begin the miscellaneous curb and sidewalk replacements in the middle of July.
June 18, 2026 – The contractor does not yet have a firm start date but anticipates curb and gutter and sidewalk replacements to begin early to mid-July. the manhole and catch basin repairs may begin sooner depending on crew availability.
The contract was awarded to Ulland Brothers, they tentatively plan to begin the manhole and catch basin repairs the week of June 8-12.