2025 Neighborhood Improvement Project Updates – Job 2501

August 1, 2025 – Ulland Brothers will start work on this project the week of August 4–8. The first phase of the project will be the replacement of settled or damaged sections of concrete curb & gutter on Lake Chapeau Drive and the Crossroads Blvd area. They will also remove the pavement and begin work on the portion of Betha Larson Lane that is being reconstructed. The reconstruction work is expected to last one to two weeks. Work on this section of road will be phased in order to allow access to the affected businesses at all times. Once this work is complete, the contractor will begin the process of edge milling and overlay the streets.

A firm start date has not been set for the work on SE Marshall Street, but work is expected to begin within the next two to three weeks.