Look for detour of Southeast Marshall
City News August 15, 2025
Work is scheduled to begin the week of Aug. 18 on Southeast Marshall Street. The project includes replacing the culvert between Blake Avenue and Interstate 35. Traffic will detour to East Main Street while this work is taking place. In other project updates, work will continue the week of Aug. 18 on Betha Larson Lane and Garfield Avenue between Fairlane Terrace and Richway Drive. The 11th Street reconstruction is done for this season, except for turf restoration and minor items, with the final asphalt layer set for spring of 2026. Keep following us for project updates.